Gravity Sewer Installation

Project Name:
Wardens Bay, Isle of Sheppey
Gravity Sewer Installation

Client: Southern Water

Requirements:
3 x drills in various lengths

Ground Conditions:
Clay turning into sand and ballast

Length:
Drill 1 - 37m, Drill 2 - 142m, Drill 3 - 96m

Obstacles:
Main road in Wardens Bay,
static caravans in park

Duration:
4 days working 07:30 - 1730